2018 2019 2020
Estimated Start Estimated Completion J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Pre-Construction Activities Jan-18 Apr-18
Design: Phase 1 & Phase 2 Feb-18 Apr-18
Construction: Phase 1 – Pavement Rehabilitation May-18 Jan-19
Construction: Phase 2 – Shoulder Widening (Increments 1 & 5) Aug-18 Jan-19
Construction: Phase 2 – Shoulder Widening (Increments 2, 3, 4) Jan-19 Feb-20

*Yellow bar indicates limited construction activities occurring.

==================================================================================================================

 

Beginning in early April, construction activities will commence on the Rice Street portion of the Lihue Town Core Mobility and Revitalization project, a County of Kaua’i, Department of Public Works project. Construction is expected to be complete by end of 2019.

The area of work is shown under Phase 1A below. Work will start at the Western end of Rice Street and head East on the Southside of the roadway. Work hours are 7:00am to 5:30pm, Monday through Friday.

Motorists are encouraged to use alternate routes or allow for extra travel time when driving near the work area as well as observe and follow all construction traffic controls. Please exercise caution when commuting through the work area.

Construction activities include:

  • Installation of Best Management Practices (biosocks, drain inlet protection)
  • Demolition and grading for new concrete curb and gutter, sidewalks, parking and driveway paving
  • Installation of drainage structures and improvements
  • Installation of concrete curb and gutter and sidewalks, parking and driveway paving
  • Installation of bus shelters, Rectangular Rapid Flashing Beacons (RRFB’s), traffic signals, landscaping and site furnishings
  • Asphalt paving and restriping of the roadway

====================================================================================================================

 

Beginning Monday, March 4, 2019, construction activities will commence on the Eiwa Street, Pi’ikoi Parking Lot and Umi Street, (Sites 6 & 7), portion of the Lihue Town Core Mobility and Revitalization project. The area of work is shown under Phase 2 below. Work hours are 7:00am to 5:30pm, Monday through Friday.

Motorists are encouraged to allow for extra travel time when driving near the work area and observe/ follow all construction traffic controls. Please exercise caution when commuting through the work area.

Construction activities include:

  • Installation of Best Management Practices (biosocks, drain inlet protection)
  • Demolition and grading for new concrete curb and gutter, sidewalks, parking and driveway paving
  • Demolition of Pi’ikoi Building Extension
  • Installation of drainage structures and improvements
  • Installation of concrete curb and gutter and sidewalks, parking and driveway paving
  • Roadway reconstruction

The County of Kauai and Kiewit Infrastructure West Co., thank you for your patience and understanding during these operations.

View the latest design drawings for this work HERE        

Construction Progress

                         

The Civic Center Path is designed to be  10 feet wide.  Excavation and embankment of the shared use path shown near Hardy Street.